Road Closure Information near Riverside Bristol

Road Closure Information near Riverside Bristol

Over the next couple of years there will be road works extending the metrobus route along Gipsy Patch Lane and replacing the railway bridge.
This will mean that sometimes Gipsy Patch Lane is closed around the railway bridge area, or that there may be traffic lights somewhere along Gipsy Patch Lane.
Riverside will be open as normal throughout, but the works will cause disruption to traffic so you may want to make alternative route plans to get here.

TIMETABLE FOR WORKS

June 2019
Four week closure of Gipsy Patch Lane for utility diversions. Station Road open both ends, but possibly lights controlling Gipsy Patch end.
Summer 2019
CPME construction starts alongside utility diversions.
2020
Gipsy Patch Lane bridge construction.
Early 2020
Eight month closure of Gipsy Patch Lane for bridge and highway works.
Late 2020
Bridge construction complete. Roadworks for new bus lanes and metrobus stops continue with traffic management.
2021
Roadworks for new bus lanes and metrobus stops continue with ongoing traffic management.
Early 2022
Construction complete and metrobus services operating on the CPME route.
This information from South Gloucestershire Council is correct as we currently have it. If schedules change we will keep you up to date as soon as possible.
For further information please contact CPmetrobus@southglos.gov.uk
or go to www.southglos.gov.uk/CPmetrobus